Home
›
Electric trucks
›
Charging electric trucks in the UK: depot, public hubs and cost per kWh

Charging electric trucks in the UK: depot, public hubs and cost per kWh

The UK's public HGV charging network is young: Milence opened its first UK hub at Immingham, GRIDSERVE's Electric Freightway is building HGV chargers at motorway services, Aegis Energy is developing multi-energy hubs and Zenobē electrifies depots on a financed model – all under the government's £200m ZEHID demonstrator programme. Public HGV charging costs around 40p/kWh ex VAT (Milence £0.399), depot electricity 22–26p on a business tariff. 80–90 % of the energy should be charged at your own yard – and that is where the second half of the investment sits: charger, civil works, grid connection, £65–80k per e-truck before the 70 % Depot Charging Scheme.

The network in numbers

  • ZEHID: the Zero Emission HGV and Infrastructure Demonstrator (£200 million, 2024–2030) funds four consortia – eFREIGHT 2030, Electric Freightway (GRIDSERVE), ZENFreight (Zenobē/Voltempo) and Project HyHAUL (hydrogen) – with around 370 zero-emission HGVs and 57 charging or refuelling sites across the UK.
  • Milence Immingham: the first UK hub of the Daimler/Traton/Volvo joint venture, near the Humber ports; further sites along the M1/M6/M62 corridors planned, MCS retrofits from 2026.
  • GRIDSERVE Electric Freightway: HGV charging at Moto and other motorway service areas, 360 kW+ CCS, MCS-ready bays.
  • Aegis Energy: multi-energy HGV hubs (electric, HVO, later hydrogen), first sites in the Midlands and North West.
  • Zenobē: depot electrification with financing, batteries and grid connection – the model for fleets that do not want to own the infrastructure.
  • Public MCS: single digits in 2026; plan on CCS 350–400 kW en route and depot charging overnight.
  • ≈1,800 truck-capable charging points on Europe's main corridors (Milence count, 2026) – relevant for cross-Channel traffic.

What charging costs (p/kWh ex VAT)

  • Depot, overnight, business tariff: 22–26 – the standard, 80–90 % of all kWh.
  • Depot with time-of-use tariff and load management: 12–18 – overnight wholesale 6–8p plus network charges; pays off from ~5 vehicles.
  • Public CCS 350–400 kW, contract tariff (Milence): 39.9 – top-up charging en route.
  • Public HPC ad hoc: 45–55 (estimate) – the exception.

Depot investment case: what a charge point costs

The e-truck is only half of the investment. The other half stands in the yard – and without it the truck does not run. Estimates ex VAT 2026, range ±30 %, before the 70 % Depot Charging Scheme.

  • Power per truck: 350 km/day ≈ 400 kWh; with 9 h dwell time, 50–100 kW is enough. Only two- or three-shift operations need megawatt charging.
  • DC charge point: 50 kW ~£22k, 100 kW ~£30k, 200 kW ~£47k, 400 kW ~£80k, MCS from ~£215k (hardware incl. installation).
  • Civil works: cable route, foundation, sub-distribution: £9–22k per charge point – the item most often underestimated.
  • Grid connection: up to ~250 kW on low voltage; above that an HV connection with a transformer (630 kVA ~£95k, 1 MVA ~£140k, 1.6 MVA ~£200k) plus the DNO connection charge. Check the DNO's capacity map first – in constrained areas the connection, not the charger, sets the timeline.
  • Load management: £9–13k one-off, £1–2k/year backend; cuts the required connection capacity by ~30 %.
  • Per e-truck, all in: 2 trucks ~£65k per truck (low voltage, no transformer) · 5 trucks ~£80k (from ~250 kW a transformer of ~£95k becomes necessary and is spread over only 5 vehicles) · 10 trucks ~£73k · 20 trucks ~£65k. With the 70 % grant (cap £1m per organisation) that becomes £20–24k per truck – enter that value in the TCO calculator.

What is technically required

  1. Request a connection from your DNO (capacity in kW, site, timeline) – 2 e-trucks need 100–200 kW, 10 e-trucks ~700 kW; lead time 6–18 months, so do this first.
  2. Derive the charging profile from the route schedule: daily consumption ÷ dwell time = charging power per truck; an overnight window of 6–8 h is usually enough for 100 kW per vehicle.
  3. Plan parking bays with manoeuvring space, foundations and the cable route to the substation; from 250 kW plan for a transformer and LV main distribution.
  4. Load management with an OCPP backend; fire-safety concept agreed with the insurer.
  5. Negotiate an electricity contract with time windows and cap peak demand (capacity charges); cost solar and storage as a second stage.
  6. Apply for the Depot Charging Scheme in the current window (28 October 2026 – 29 January 2027) before ordering hardware.
  7. Check core routes against Milence, Electric Freightway and Aegis sites; plan for public MCS from 2027 at the earliest.

DfT/Innovate UK (ZEHID), Milence, GRIDSERVE, Aegis Energy, Zenobē, Ofgem and business tariff surveys (Q1 2026), Milence UK price list, ICCT. As of September 2026.

Frequently asked questions

Short, concrete answers. Figures from the Electric Hub, as of September 2026.

Frage

Antwort

What is your diesel worth today?

Anyone switching to electric has one diesel too many in the yard. Vetted dealers from 35+ countries make binding offers – valuation within 24 hours, free of charge.

Get a free valuation